Project Overview

 

Prologik undertook a significant modernisation project for a Dubai-based food production facility of a renowned chocolate brand. The project scope was comprehensive, encompassing an upgrade from the traditional InTouch system to the advanced Wonderware System Platform and the setup of all necessary servers. The initiative also focused on standardising Programmable Logic Controllers (PLCs) to the company’s specifications, integrating new conche mixers, and developing a custom SQL-based recipe and batch tracking system.

 

Key Challenges

 

Complex Coordination:

Coordinating with the engineering team in Dubai required meticulous planning and precise communication, particularly due to time zone differences.

Language Barriers:

Overcoming language differences posed a challenge, necessitating clear and effective communication strategies.

Remote Project Execution:

Managing the project remotely introduced unique challenges in ensuring all components were fully integrated and functional without immediate physical oversight.

 

Solution Implementation

 

Integrated, User-Friendly Recipe System:

Prologik developed a bespoke SQL-based recipe and batch tracking system tailored to the client’s specific needs, ensuring ease of use and accuracy.

Virtual Simulations:

Conducted extensive virtual simulations with active client involvement to ensure all systems functioned as intended before physical implementation.

Standardisation of PLCs:

Standardised the facility’s PLCs to Rockwell L83Es, ensuring consistency and reliability in the production process.

Effective Communication Tools:

Utilised Allen Bradley software for smooth integration and Microsoft Teams for consistent and clear communication with the Dubai team.

 

Commissioning & Impact

 

The project was executed with an innovative approach of three weeks of virtual commissioning followed by only six days of on-site work. This method proved highly efficient, allowing for thorough testing and troubleshooting in a virtual environment before the physical setup. The combination of virtual and physical commissioning led to:

 

Rapid Completion:

Achieved the project’s objectives in record time with minimal on-site presence.

High Client Satisfaction:

The client expressed high satisfaction with the process and outcomes, highlighting the efficiency and effectiveness of the solution.

Minimal Rework:

The meticulous planning and virtual commissioning phase resulted in minimal rework during the on-site phase, ensuring a smooth transition and integration.

 

Lessons Learned

 

Value of Virtual Commissioning:

The success of this project underscored the importance and effectiveness of virtual commissioning, especially for international projects.

Client Engagement:

Active involvement of the client throughout the project, particularly during the virtual simulations, was crucial in ensuring the system met all requirements and functioned as intended.

 

OUR CASE STUDIES